1 / 150
2 / 150
3 / 150
4 / 150
5 / 150
6 / 150
7 / 150
8 / 150
Question 9 of 150
A construction PM uses parametric estimating: $200 per square foot for office buildings. A new 50,000 sq ft office is planned. What is the parametric estimate?
9 / 150
10 / 150
11 / 150
12 / 150
13 / 150
14 / 150
15 / 150
16 / 150
17 / 150
18 / 150
19 / 150
Question 20 of 150
Using the PERT (Beta) formula, a work package has O=$10,000, M=$15,000, P=$26,000. What is the expected cost?
20 / 150
21 / 150
22 / 150
23 / 150
Question 24 of 150
A project's critical path has an expected cost of $500,000 with a standard deviation of $30,000. What is the range for a 95% confidence interval?
24 / 150
25 / 150
Question 26 of 150
A PM estimates 50 work packages using three-point estimating and calculates the total project expected cost as $2,000,000 with a total standard deviation of $150,000. The sponsor asks: 'What budget should we approve to have a 95% confidence of not exceeding it?' What is the answer?
26 / 150
27 / 150
28 / 150
29 / 150
Question 30 of 150
A project has BAC=$100,000. At month 6, 45% of the work is planned to be complete and 40% is actually complete. Actual spending is $42,000. What are PV, EV, and AC?
30 / 150
31 / 150
32 / 150
33 / 150
34 / 150
35 / 150
Question 36 of 150
A project has BAC=$500,000, EV=$200,000, AC=$250,000. CPI=0.80. If future performance continues at the same CPI, what is the Estimate at Completion (EAC)?
36 / 150
37 / 150
Question 38 of 150
A project has BAC=$400,000, EV=$160,000, AC=$180,000. The PM believes the initial cost variance was caused by a one-time vendor issue that is now resolved. What EAC formula should the PM use?
38 / 150
39 / 150
Question 40 of 150
A project has BAC=$300,000. At 50% completion, EV=$150,000 and AC=$180,000. CPI=0.833. What is VAC (Variance at Completion)?
40 / 150
41 / 150
42 / 150
43 / 150
44 / 150
Question 45 of 150
A project has completed 6 months of a 12-month timeline. EVM data: BAC=$1,200,000, PV=$600,000, EV=$540,000, AC=$590,000. Calculate all key EVM metrics.
45 / 150
46 / 150
Question 47 of 150
A PM uses the EAC formula that incorporates both CPI and SPI: EAC = AC + (BAC-EV)/(CPI x SPI). With BAC=$800K, EV=$400K, AC=$450K, CPI=0.889, SPI=0.870, what is the EAC?
47 / 150
48 / 150
49 / 150
50 / 150
51 / 150
52 / 150
53 / 150
54 / 150
55 / 150
56 / 150
57 / 150
58 / 150
59 / 150
60 / 150
Question 61 of 150
A project has a Budget at Completion (BAC) of $1,000,000. The PM calculates contingency reserve at 12% of the cost estimate and management reserve at 5% of the cost baseline. What is the total project budget?
61 / 150
Question 62 of 150
A project manager uses Earned Value Management and reports EAC = $550,000 against a BAC of $500,000. The project has $60,000 in contingency reserve (part of the $500,000 baseline) and $40,000 in management reserve. Should the PM be concerned?
62 / 150
63 / 150
64 / 150
65 / 150
Question 66 of 150
A project has the following EVM data: BAC=$600K, PV=$300K, EV=$270K, AC=$310K. The PM needs to present a comprehensive status report. What should the report include?
66 / 150
67 / 150
68 / 150
Question 69 of 150
A PM uses EVM on an agile project. The project has 200 story points total (BAC=$200,000 at $1,000/point). After Sprint 5, 80 points are complete and $90,000 has been spent. What are the EVM metrics?
69 / 150
70 / 150
71 / 150
72 / 150
73 / 150
74 / 150
75 / 150
Question 76 of 150
A PM manages a $2M project. At 30% completion, EVM shows: EV=$600K, AC=$650K, PV=$700K. Calculate all EVM metrics and provide a comprehensive assessment.
76 / 150
77 / 150
78 / 150
79 / 150
80 / 150
81 / 150
82 / 150
83 / 150
84 / 150
85 / 150
86 / 150
87 / 150
88 / 150
89 / 150
90 / 150
91 / 150
92 / 150
93 / 150
94 / 150
95 / 150
Question 96 of 150
A PM calculates the project's 'cost of quality' (COQ). What are the four categories of COQ?
96 / 150
97 / 150
Question 98 of 150
A PM estimates a large project in phases: Phase 1 uses bottom-up estimating ($500K), Phase 2 uses parametric ($800K estimate with +/- 20% range), and Phase 3 uses analogous ($400K rough estimate). How should the PM present the total project budget?
98 / 150
99 / 150
100 / 150
101 / 150
102 / 150
103 / 150
104 / 150
105 / 150
Question 106 of 150
An organization evaluates three projects: Project A (NPV=$50K, IRR=15%, BCR=1.3), Project B (NPV=$80K, IRR=12%, BCR=1.2), Project C (NPV=$30K, IRR=20%, BCR=1.5). The organization can only fund one project. Which financial metric should be the PRIMARY decision driver?
106 / 150
107 / 150
108 / 150
109 / 150
Question 110 of 150
A PM discovers that the project's indirect costs (overhead, facilities, administration) are allocated at 40% of direct labor costs. The project has $300,000 in direct labor. What are the total loaded costs?
110 / 150
111 / 150
112 / 150
113 / 150
114 / 150
115 / 150
116 / 150
117 / 150
118 / 150
119 / 150
Question 120 of 150
A PM uses 'Estimate at Completion using the Composite SPI/CPI method' on a project where SPI=0.85 and CPI=0.90. BAC=$1,000,000, EV=$400,000, AC=$444,444. What is the EAC?
120 / 150
121 / 150
122 / 150
123 / 150
124 / 150
125 / 150
126 / 150
Question 127 of 150
A PM is evaluating a project using the profitability index (PI). The project has a present value of future cash flows of $1,500,000 and requires an initial investment of $1,200,000. What is the PI and what does it mean?
127 / 150
128 / 150
129 / 150
130 / 150
Question 131 of 150
A PM uses 'cost trending' to forecast future cost performance. The last 6 months show monthly CV values of: -$5K, -$8K, -$12K, -$15K, -$20K, -$25K. What does this trend indicate?
131 / 150
132 / 150
Question 133 of 150
A PM manages a $5M project with the following EVM data at month 8 of 16: BAC=$5M, EV=$2.2M, PV=$2.5M, AC=$2.4M. What is the comprehensive financial status and forecast?
133 / 150
134 / 150
135 / 150
136 / 150
137 / 150
138 / 150
Question 139 of 150
A PM calculates that the project's cost baseline must be time-phased for cash flow management. The project has 4 quarters. Q1=$200K, Q2=$350K, Q3=$300K, Q4=$150K. The finance department requires a minimum cash balance of $50K at all times. If funding comes in equal quarterly installments, what is the minimum quarterly installment needed?
139 / 150
140 / 150
141 / 150
142 / 150
143 / 150
144 / 150
145 / 150
146 / 150
147 / 150
148 / 150
Question 149 of 150
A PM needs to choose between two schedule compression options for a critical path activity. Option 1: Crash by adding overtime ($5,000 extra cost, saves 3 days). Option 2: Fast-track with another activity ($0 direct cost, saves 3 days, 25% probability of 5-day rework at $2,000/day). Which option has the lower EXPECTED total cost?
149 / 150
150 / 150