← Exams · PMP

PMBOK 7 - Cost & Finance

Learning Objectives

Estimating: Analogous, Parametric, Bottom-up, Three-point. EVM: CV, SV, CPI, SPI, EAC, ETC, TCPI. Funding: Management vs. Contingency reserves.

Exams certification badge
Time left --:--:--
Question 1 / 150 · 150 unanswered
Question 1 of 150
What is analogous estimating and when is it MOST appropriate to use?
1 / 150
Question 2 of 150
A PM uses analogous estimating for a new warehouse construction project based on a similar warehouse completed last year for $2M. The new warehouse is 20% larger. What is the analogous estimate?
2 / 150
Question 3 of 150
What is the primary LIMITATION of analogous estimating?
3 / 150
Question 4 of 150
A PM has historical data from three similar projects: Project A ($1.5M), Project B ($1.8M), Project C ($2.1M). Which approach provides the BEST analogous estimate?
4 / 150
Question 5 of 150
A PM uses analogous estimating at project initiation and produces a rough order of magnitude (ROM) estimate of $500,000. What accuracy range is typically associated with a ROM estimate?
5 / 150
Question 6 of 150
How does analogous estimating differ from expert judgment in cost estimation?
6 / 150
Question 7 of 150
A PM is estimating a software project and finds that the only reference project used a completely different technology stack. Should the PM still use analogous estimating?
7 / 150
Question 8 of 150
What is parametric estimating and how does it differ from analogous estimating?
8 / 150
Question 9 of 150
A construction PM uses parametric estimating: $200 per square foot for office buildings. A new 50,000 sq ft office is planned. What is the parametric estimate?
9 / 150
Question 10 of 150
For parametric estimating to be reliable, what two conditions must the statistical model meet?
10 / 150
Question 11 of 150
A software PM uses function point analysis as a parametric model. The model shows 800 function points at $600/FP = $480,000. However, the project uses a new programming language the team has never used before. How should the PM adjust the estimate?
11 / 150
Question 12 of 150
A PM combines parametric and analogous estimating. The parametric model estimates $1.2M but is based on limited data. An analogous estimate from a similar project is $1.4M. How should the PM reconcile these?
12 / 150
Question 13 of 150
A PM uses a parametric model: cost = $50 per line of code. The project estimates 100,000 lines of code. A developer argues this model is flawed. What is the MOST likely criticism?
13 / 150
Question 14 of 150
What is a 'learning curve' in parametric estimating and how does it affect cost estimates for repetitive work?
14 / 150
Question 15 of 150
What is bottom-up estimating and when does it produce the MOST accurate results?
15 / 150
Question 16 of 150
A PM uses bottom-up estimating with 200 work packages. Each work package is estimated by the team member who will perform the work. What advantage does this provide over top-down estimating?
16 / 150
Question 17 of 150
A PM compares three estimates for the same project: Analogous = $2M, Parametric = $2.3M, Bottom-up = $2.5M. The bottom-up is highest. What commonly explains why bottom-up estimates tend to be higher?
17 / 150
Question 18 of 150
A PM has a project with a well-defined WBS for 80% of the scope but the remaining 20% is undefined. How should the PM estimate the total project cost?
18 / 150
Question 19 of 150
What is three-point estimating and what are the three estimates used?
19 / 150
Question 20 of 150
Using the PERT (Beta) formula, a work package has O=$10,000, M=$15,000, P=$26,000. What is the expected cost?
20 / 150
Question 21 of 150
What is the difference between the triangular distribution formula and the PERT (Beta) distribution formula for three-point estimating?
21 / 150
Question 22 of 150
Using three-point estimating, a PM calculates the standard deviation for a work package with O=8 days, M=12 days, P=22 days. What is the standard deviation?
22 / 150
Question 23 of 150
A PM uses three-point estimating for 5 work packages on the critical path and calculates their expected durations and standard deviations. The expected path duration is 50 days. How is the path standard deviation calculated?
23 / 150
Question 24 of 150
A project's critical path has an expected cost of $500,000 with a standard deviation of $30,000. What is the range for a 95% confidence interval?
24 / 150
Question 25 of 150
A PM uses three-point estimating and discovers that one work package has O=$50,000, M=$55,000, P=$200,000. The wide pessimistic range concerns the sponsor. What does this spread indicate?
25 / 150
Question 26 of 150
A PM estimates 50 work packages using three-point estimating and calculates the total project expected cost as $2,000,000 with a total standard deviation of $150,000. The sponsor asks: 'What budget should we approve to have a 95% confidence of not exceeding it?' What is the answer?
26 / 150
Question 27 of 150
When combining three-point estimates with bottom-up estimating, what is the recommended approach?
27 / 150
Question 28 of 150
A PM presents a project budget of $1,000,000 based on three-point estimating. A stakeholder asks: 'Is this the most likely cost, the average cost, or the guaranteed cost?' How should the PM respond?
28 / 150
Question 29 of 150
What are the three fundamental measurements in Earned Value Management (EVM)?
29 / 150
Question 30 of 150
A project has BAC=$100,000. At month 6, 45% of the work is planned to be complete and 40% is actually complete. Actual spending is $42,000. What are PV, EV, and AC?
30 / 150
Question 31 of 150
What is Cost Variance (CV) and how is it calculated?
31 / 150
Question 32 of 150
What is Schedule Variance (SV) and how is it calculated?
32 / 150
Question 33 of 150
What is the Cost Performance Index (CPI) and what does a CPI of 0.85 mean?
33 / 150
Question 34 of 150
What is the Schedule Performance Index (SPI) and what does an SPI of 1.15 mean?
34 / 150
Question 35 of 150
A project has EV=$200,000, PV=$220,000, AC=$210,000. Calculate CV, SV, CPI, and SPI. What is the project's status?
35 / 150
Question 36 of 150
A project has BAC=$500,000, EV=$200,000, AC=$250,000. CPI=0.80. If future performance continues at the same CPI, what is the Estimate at Completion (EAC)?
36 / 150
Question 37 of 150
What are the four common EAC formulas and when is each used?
37 / 150
Question 38 of 150
A project has BAC=$400,000, EV=$160,000, AC=$180,000. The PM believes the initial cost variance was caused by a one-time vendor issue that is now resolved. What EAC formula should the PM use?
38 / 150
Question 39 of 150
What is ETC (Estimate to Complete) and how is it related to EAC?
39 / 150
Question 40 of 150
A project has BAC=$300,000. At 50% completion, EV=$150,000 and AC=$180,000. CPI=0.833. What is VAC (Variance at Completion)?
40 / 150
Question 41 of 150
What is the To-Complete Performance Index (TCPI) and what does it measure?
41 / 150
Question 42 of 150
A project has BAC=$500,000, EV=$200,000, AC=$250,000. What is TCPI(BAC) and what does it indicate?
42 / 150
Question 43 of 150
A project has BAC=$400K, EV=$200K, AC=$220K, EAC=$440K. Calculate TCPI(EAC). What does it tell management?
43 / 150
Question 44 of 150
A PM reviews EVM data: CPI=0.92, SPI=0.88, TCPI(BAC)=1.15. The sponsor asks if the project can meet the original budget. What should the PM advise?
44 / 150
Question 45 of 150
A project has completed 6 months of a 12-month timeline. EVM data: BAC=$1,200,000, PV=$600,000, EV=$540,000, AC=$590,000. Calculate all key EVM metrics.
45 / 150
Question 46 of 150
At what project completion percentage does CPI typically stabilize and become a reliable predictor of final cost performance?
46 / 150
Question 47 of 150
A PM uses the EAC formula that incorporates both CPI and SPI: EAC = AC + (BAC-EV)/(CPI x SPI). With BAC=$800K, EV=$400K, AC=$450K, CPI=0.889, SPI=0.870, what is the EAC?
47 / 150
Question 48 of 150
SPI has a known limitation: it always approaches 1.0 as the project nears completion, even for severely delayed projects. Why does this happen?
48 / 150
Question 49 of 150
A PM tracks EVM monthly. In Month 1, CPI=1.05. Month 2, CPI=0.98. Month 3, CPI=0.91. Month 4, CPI=0.85. What trend should concern the PM?
49 / 150
Question 50 of 150
A project shows CPI=1.10 (under budget) but SPI=0.75 (significantly behind schedule). What does this combination likely indicate?
50 / 150
Question 51 of 150
What is the difference between a contingency reserve and a management reserve in project budgeting?
51 / 150
Question 52 of 150
A project has a cost estimate of $400,000 and a contingency reserve of $50,000. What is the cost baseline?
52 / 150
Question 53 of 150
A project budget structure shows: Activity estimates ($300K) + Contingency reserve ($40K) = Cost baseline ($340K) + Management reserve ($20K) = Project budget ($360K). What level of funding authorization is needed from the sponsor?
53 / 150
Question 54 of 150
How is contingency reserve typically calculated?
54 / 150
Question 55 of 150
During project execution, a risk identified in the risk register materializes. The risk response costs $15,000 from the $50,000 contingency reserve. What happens to the cost baseline?
55 / 150
Question 56 of 150
An unforeseen event occurs that was NOT in the risk register. The PM needs $25,000 to address it. Where should this funding come from?
56 / 150
Question 57 of 150
A PM notices that contingency reserve is being used faster than expected. After 40% of the project, 70% of the contingency is consumed. What should the PM do?
57 / 150
Question 58 of 150
A project is 80% complete. No major risks remain and only $5,000 of the $50,000 contingency reserve has been used. What should happen to the unused contingency?
58 / 150
Question 59 of 150
How does the concept of 'funding limit reconciliation' relate to project budgets and reserves?
59 / 150
Question 60 of 150
A PM creates an S-curve showing cumulative planned expenditure over the project timeline. What does the S-curve represent and why is it useful?
60 / 150
Question 61 of 150
A project has a Budget at Completion (BAC) of $1,000,000. The PM calculates contingency reserve at 12% of the cost estimate and management reserve at 5% of the cost baseline. What is the total project budget?
61 / 150
Question 62 of 150
A project manager uses Earned Value Management and reports EAC = $550,000 against a BAC of $500,000. The project has $60,000 in contingency reserve (part of the $500,000 baseline) and $40,000 in management reserve. Should the PM be concerned?
62 / 150
Question 63 of 150
A PM reports that the project will use $30,000 of management reserve to address an unforeseen regulatory requirement. How does this affect the cost baseline?
63 / 150
Question 64 of 150
What is the relationship between risk management and contingency reserve sizing?
64 / 150
Question 65 of 150
An organization requires all projects to carry a 10% management reserve regardless of project risk profile. A low-risk internal project and a high-risk innovation project both have $1M budgets and thus both carry $100K management reserve. What is wrong with this approach?
65 / 150
Question 66 of 150
A project has the following EVM data: BAC=$600K, PV=$300K, EV=$270K, AC=$310K. The PM needs to present a comprehensive status report. What should the report include?
66 / 150
Question 67 of 150
A project has CPI=1.05 and SPI=0.80. The sponsor asks: 'Are we in good shape since we are under budget?' Why is this interpretation dangerous?
67 / 150
Question 68 of 150
A project is 25% complete. CPI=0.85 and is declining. The PM calculates TCPI(BAC)=1.22. A team lead suggests 'working smarter' to improve efficiency by 22%. Is this realistic?
68 / 150
Question 69 of 150
A PM uses EVM on an agile project. The project has 200 story points total (BAC=$200,000 at $1,000/point). After Sprint 5, 80 points are complete and $90,000 has been spent. What are the EVM metrics?
69 / 150
Question 70 of 150
A PM calculates two EAC values: EAC1 = BAC/CPI = $625,000 and EAC2 = AC + (BAC-EV)/(CPI x SPI) = $700,000. Why are they different and which should the PM use?
70 / 150
Question 71 of 150
What is the Budget at Completion (BAC) and can it change during the project?
71 / 150
Question 72 of 150
A PM is deciding whether to re-baseline the project after significant scope changes. What factors should the PM consider?
72 / 150
Question 73 of 150
A PM presents EVM data showing CPI=0.95 and SPI=1.05. The sponsor says this is acceptable. Is the sponsor's assessment correct?
73 / 150
Question 74 of 150
What is 'Earned Schedule' (ES) and why was it developed?
74 / 150
Question 75 of 150
A PM tracks cost and schedule performance metrics. The project shows: positive CV (under budget), positive SV (ahead of schedule), CPI > 1.0, SPI > 1.0. Is this always good news?
75 / 150
Question 76 of 150
A PM manages a $2M project. At 30% completion, EVM shows: EV=$600K, AC=$650K, PV=$700K. Calculate all EVM metrics and provide a comprehensive assessment.
76 / 150
Question 77 of 150
A PM is asked to forecast the project completion date using EVM. The original project duration is 12 months. At month 6, SPI=0.80. What is the forecasted project duration?
77 / 150
Question 78 of 150
A PM observes that a project's CPI has been consistently between 0.90 and 0.93 for the last 5 reporting periods. The PM proposes re-estimating the remaining work bottom-up rather than using CPI-based forecasting. When is this approach appropriate?
78 / 150
Question 79 of 150
A government project requires reporting Cost Performance Baseline (CPB) separately from CPI. What is CPB and how does it differ from standard CPI?
79 / 150
Question 80 of 150
A PM uses the EAC formula with SPI factor: EAC = AC + (BAC-EV)/(CPI x SPI). Under what circumstances would this produce a significantly different result from EAC = BAC/CPI?
80 / 150
Question 81 of 150
A PM needs to explain to a non-technical stakeholder why the project should not be cancelled even though CPI=0.88. The project has delivered $440,000 of value (EV) against $500,000 spent (AC). What argument supports continuing?
81 / 150
Question 82 of 150
What is the difference between Work Performance Data, Work Performance Information, and Work Performance Reports in the context of EVM?
82 / 150
Question 83 of 150
A PM calculates that TCPI(BAC)=1.35 for a project that is 40% complete. The management team insists on meeting the original budget. What should the PM recommend?
83 / 150
Question 84 of 150
In EVM, what does a positive Schedule Variance (SV) that has been consistently positive for the last 6 months suddenly turning negative indicate?
84 / 150
Question 85 of 150
A PM is managing 5 projects in a portfolio. Each project reports EVM metrics. How can the PM aggregate EVM data for portfolio-level reporting?
85 / 150
Question 86 of 150
A PM is developing the project budget. What is the correct sequence of steps from cost estimation to budget approval?
86 / 150
Question 87 of 150
A project sponsor imposes a budget ceiling of $2M, but the bottom-up estimate shows $2.4M. How should the PM reconcile this $400K gap?
87 / 150
Question 88 of 150
A PM uses vendor quotes to estimate procurement costs. Three vendors quote: $80K, $95K, $120K. How should the PM use these quotes in the cost estimate?
88 / 150
Question 89 of 150
What is a 'control account' in cost management and how does it relate to the WBS?
89 / 150
Question 90 of 150
A PM estimates a project using three techniques and gets: Analogous=$1.5M, Parametric=$1.7M, Bottom-up=$1.9M. The PM needs to present a single budget request. What approach reconciles these three estimates?
90 / 150
Question 91 of 150
What is 'cost aggregation' and why is it important in budget development?
91 / 150
Question 92 of 150
A PM uses 'reserve analysis' during project monitoring. At 50% completion, the project has used 30% of its contingency reserve. Is this acceptable?
92 / 150
Question 93 of 150
A PM discovers that the project's cost estimate did not include inflation adjustment for a 3-year project. Material costs are expected to increase 5% annually. The base material cost is $200,000. What is the impact?
93 / 150
Question 94 of 150
A PM uses 'value engineering' to reduce project costs. How does value engineering work and what must the PM ensure?
94 / 150
Question 95 of 150
A PM negotiates a project budget. The finance department applies a 15% blanket cut to the bottom-up estimate 'because estimates always include padding.' How should the PM respond?
95 / 150
Question 96 of 150
A PM calculates the project's 'cost of quality' (COQ). What are the four categories of COQ?
96 / 150
Question 97 of 150
A PM uses 'parametric estimating with regression analysis.' What does regression analysis add to basic parametric estimating?
97 / 150
Question 98 of 150
A PM estimates a large project in phases: Phase 1 uses bottom-up estimating ($500K), Phase 2 uses parametric ($800K estimate with +/- 20% range), and Phase 3 uses analogous ($400K rough estimate). How should the PM present the total project budget?
98 / 150
Question 99 of 150
A PM must choose between 'definitive estimate' and 'budget estimate' accuracy levels for a project approaching the execution phase. What accuracy range does each represent?
99 / 150
Question 100 of 150
A PM is asked: 'What is the most important thing about project cost management?' From a PMBOK 7 perspective, what is the best answer?
100 / 150
Question 101 of 150
A PM evaluates two projects for selection using NPV. Project A costs $100K upfront and returns $30K per year for 5 years at a 10% discount rate. Project B costs $200K upfront and returns $55K per year for 5 years at 10%. Which project has the higher NPV?
101 / 150
Question 102 of 150
A project has an initial investment of $500,000. Annual net cash flows are: Year 1=$150K, Year 2=$180K, Year 3=$200K, Year 4=$170K. At what point is the payback achieved?
102 / 150
Question 103 of 150
What does a Benefit-Cost Ratio (BCR) of 1.4 indicate about a project?
103 / 150
Question 104 of 150
A PM compares ROI for two projects. Project X: cost $200K, benefit $300K. Project Y: cost $500K, benefit $700K. Which has the higher ROI?
104 / 150
Question 105 of 150
What is the Internal Rate of Return (IRR) and how is it used in project selection?
105 / 150
Question 106 of 150
An organization evaluates three projects: Project A (NPV=$50K, IRR=15%, BCR=1.3), Project B (NPV=$80K, IRR=12%, BCR=1.2), Project C (NPV=$30K, IRR=20%, BCR=1.5). The organization can only fund one project. Which financial metric should be the PRIMARY decision driver?
106 / 150
Question 107 of 150
A project has a sunk cost of $100,000 from a failed Phase 1. The PM must decide whether to proceed with Phase 2 which requires $200,000 and will generate $250,000 in benefits. Should the sunk cost influence the decision?
107 / 150
Question 108 of 150
What is 'opportunity cost' in project selection and why does it matter?
108 / 150
Question 109 of 150
A PM uses 'life cycle costing' to evaluate a project. What does life cycle costing include beyond the project budget?
109 / 150
Question 110 of 150
A PM discovers that the project's indirect costs (overhead, facilities, administration) are allocated at 40% of direct labor costs. The project has $300,000 in direct labor. What are the total loaded costs?
110 / 150
Question 111 of 150
A PM needs to understand the difference between fixed costs and variable costs for budget management. How do they behave differently?
111 / 150
Question 112 of 150
A PM is asked about 'direct costs' versus 'indirect costs.' A team member's salary is 100% dedicated to the project. Is this a direct or indirect cost?
112 / 150
Question 113 of 150
A PM manages a project with a 'time and materials' (T&M) budget structure. What unique challenge does T&M create for cost management compared to a fixed-price budget?
113 / 150
Question 114 of 150
A PM calculates that the project's cost of poor quality (COPQ) is 25% of total project cost. What does this indicate and what should the PM do?
114 / 150
Question 115 of 150
A PM uses 'Earned Value to manage funding drawdowns.' The project's funding comes in quarterly installments. EV=$400K at end of Q2 against PV=$450K. The Q3 funding installment is $150K. What should the PM verify?
115 / 150
Question 116 of 150
A PM presents an EAC of $1.2M against a BAC of $1M. The sponsor asks: 'How confident are you in this forecast?' What factors affect the confidence level of an EAC forecast?
116 / 150
Question 117 of 150
A PM is asked whether the organization should use a 'zero-based budget' or an 'incremental budget' for the next project cycle. What is the difference?
117 / 150
Question 118 of 150
A PM tracks 'cost performance baseline' on a graph. The x-axis shows time and the y-axis shows cumulative cost. Three lines are plotted: PV (S-curve), EV, and AC. At the current date, AC is above both EV and PV. What does this visual pattern indicate?
118 / 150
Question 119 of 150
A PM must explain to a junior team member why 'percent complete' is the most critical input to EVM accuracy. Why is this?
119 / 150
Question 120 of 150
A PM uses 'Estimate at Completion using the Composite SPI/CPI method' on a project where SPI=0.85 and CPI=0.90. BAC=$1,000,000, EV=$400,000, AC=$444,444. What is the EAC?
120 / 150
Question 121 of 150
A PM calculates that TCPI(BAC) = 1.50 for a project that is 60% complete. What is the practical implication?
121 / 150
Question 122 of 150
A PM is reporting on a project where BAC was $500K, but approved changes increased the baseline to $600K. Current: EV=$400K, AC=$420K. Should the PM report CPI against the original or current baseline?
122 / 150
Question 123 of 150
A PM manages a portfolio with three projects. All three report CPI = 1.0 (on budget). Should the portfolio manager be satisfied?
123 / 150
Question 124 of 150
A PM needs to decide between two cost estimation approaches for a new, innovative project with no historical data. Neither analogous nor parametric data exists. What approach should the PM take?
124 / 150
Question 125 of 150
A PM is asked to calculate the 'cost of delay' for a project that is running 3 months late. The project's product generates $100,000 per month in revenue. What is the cost of delay?
125 / 150
Question 126 of 150
A PM uses 'target costing' for a new product development project. How does target costing work?
126 / 150
Question 127 of 150
A PM is evaluating a project using the profitability index (PI). The project has a present value of future cash flows of $1,500,000 and requires an initial investment of $1,200,000. What is the PI and what does it mean?
127 / 150
Question 128 of 150
A PM calculates the total project budget and presents it to the sponsor. The sponsor asks: 'Does this budget include profit?' What is the correct answer for an internal project?
128 / 150
Question 129 of 150
A PM discovers a cost calculation error in month 3 that understated AC by $20,000. The corrected data shows: EV=$150K, AC=$170K (corrected from $150K), PV=$160K. How does this correction affect the EVM metrics?
129 / 150
Question 130 of 150
A PM is managing a project where the team consistently completes work under budget (CPI > 1.0) but the unused funds are being repurposed to fund scope additions without formal change control. Why is this problematic?
130 / 150
Question 131 of 150
A PM uses 'cost trending' to forecast future cost performance. The last 6 months show monthly CV values of: -$5K, -$8K, -$12K, -$15K, -$20K, -$25K. What does this trend indicate?
131 / 150
Question 132 of 150
What is 'Earned Value Management System (EVMS)' and how does it differ from simply using EVM metrics?
132 / 150
Question 133 of 150
A PM manages a $5M project with the following EVM data at month 8 of 16: BAC=$5M, EV=$2.2M, PV=$2.5M, AC=$2.4M. What is the comprehensive financial status and forecast?
133 / 150
Question 134 of 150
A PM is closing a project and performs final EVM analysis. Final results: BAC=$800K, AC=$820K, all work complete (EV=$800K). What are the final metrics?
134 / 150
Question 135 of 150
A PM discovers that the project's EVM shows CPI=0.95 but the project accountant says actual costs are tracking to budget. What might explain this discrepancy?
135 / 150
Question 136 of 150
A PM needs to establish an appropriate 'Management Reserve' for a high-risk innovative project. The cost estimate is $3M with contingency reserve of $400K. What percentage of the cost baseline should management reserve represent for a high-risk project?
136 / 150
Question 137 of 150
A project has completed all work. Final EVM: BAC=$1M, EV=$1M, AC=$1.05M. Contingency reserve was $80K (within the $1M BAC). Management reserve was $50K. Actual contingency used: $30K. The $50K overrun used $20K from remaining contingency. Where did the last $30K come from?
137 / 150
Question 138 of 150
A PM is asked to compare two projects' financial viability. Project A requires $500K investment and has NPV=$120K over 3 years. Project B requires $300K investment and has NPV=$90K over 3 years. The organization has only $500K available. What should the PM recommend?
138 / 150
Question 139 of 150
A PM calculates that the project's cost baseline must be time-phased for cash flow management. The project has 4 quarters. Q1=$200K, Q2=$350K, Q3=$300K, Q4=$150K. The finance department requires a minimum cash balance of $50K at all times. If funding comes in equal quarterly installments, what is the minimum quarterly installment needed?
139 / 150
Question 140 of 150
A PM is managing a project for an external client under a Cost Plus Fixed Fee (CPFF) contract. The project is running 20% over budget. Who bears the cost overrun?
140 / 150
Question 141 of 150
A PM compares three contract types for cost risk distribution: Firm Fixed Price (FFP), Cost Plus Fixed Fee (CPFF), and Time & Materials (T&M). Rank them from most buyer risk to least buyer risk.
141 / 150
Question 142 of 150
A PM determines that the project requires both a fixed-price component (well-defined hardware procurement) and a time-and-materials component (undefined consulting work). What contract strategy should the PM use?
142 / 150
Question 143 of 150
A PM is evaluating the 'cost of capital' for project funding. The organization's weighted average cost of capital (WACC) is 8%. Why is this relevant to project selection?
143 / 150
Question 144 of 150
A PM presents a project business case showing: Investment = $1M, Benefits = $1.5M over 5 years, BCR = 1.5, IRR = 18%, NPV = $200K. The CFO asks: 'What about depreciation and tax effects?' Why might these affect the financial analysis?
144 / 150
Question 145 of 150
A PM is asked to evaluate a project using 'discounted payback period' instead of simple payback period. What is the difference?
145 / 150
Question 146 of 150
A PM is tasked with creating a 'cost management plan.' What key elements should this plan include?
146 / 150
Question 147 of 150
A PM uses 'cost-benefit analysis' to justify a $200K quality improvement initiative. The expected benefits: $50K annual rework reduction, $30K annual warranty cost reduction, and $20K annual customer satisfaction improvement. What is the payback period?
147 / 150
Question 148 of 150
A PM calculates EVM on a monthly basis. The data shows: EV has been increasing steadily, but AC has been increasing faster than EV for the last 4 months. PV has been tracking close to EV. What is the primary concern?
148 / 150
Question 149 of 150
A PM needs to choose between two schedule compression options for a critical path activity. Option 1: Crash by adding overtime ($5,000 extra cost, saves 3 days). Option 2: Fast-track with another activity ($0 direct cost, saves 3 days, 25% probability of 5-day rework at $2,000/day). Which option has the lower EXPECTED total cost?
149 / 150
Question 150 of 150
A PM is closing the project. Final cost data: BAC=$2M, AC=$1.95M, all deliverables accepted. The PM has $30K remaining in contingency reserve and $50K remaining in management reserve. What should happen to these unused reserves?
150 / 150