1 / 150
Question 2 of 150
In PDM, what are the four types of logical relationships between activities?
2 / 150
3 / 150
4 / 150
5 / 150
6 / 150
7 / 150
8 / 150
9 / 150
10 / 150
11 / 150
12 / 150
13 / 150
14 / 150
15 / 150
16 / 150
17 / 150
18 / 150
19 / 150
20 / 150
21 / 150
22 / 150
23 / 150
24 / 150
25 / 150
26 / 150
27 / 150
28 / 150
29 / 150
30 / 150
31 / 150
32 / 150
33 / 150
34 / 150
35 / 150
36 / 150
37 / 150
38 / 150
39 / 150
40 / 150
41 / 150
42 / 150
43 / 150
44 / 150
45 / 150
46 / 150
47 / 150
48 / 150
49 / 150
50 / 150
51 / 150
Question 52 of 150
A PM must reduce the project duration by 5 days. Three critical path activities can be crashed: X (cost $800/day, max 3 days), Y (cost $1,200/day, max 4 days), Z (cost $600/day, max 2 days). What is the optimal crashing sequence?
52 / 150
53 / 150
54 / 150
55 / 150
56 / 150
57 / 150
58 / 150
59 / 150
60 / 150
61 / 150
62 / 150
63 / 150
64 / 150
65 / 150
66 / 150
67 / 150
68 / 150
69 / 150
70 / 150
71 / 150
72 / 150
73 / 150
74 / 150
75 / 150
76 / 150
77 / 150
78 / 150
79 / 150
Question 80 of 150
A project has Activities A(5), B(3), C(7), D(4). Dependencies: A->C, B->C, C->D. All FS zero lag. What is Activity B's Total Float and Free Float?
80 / 150
81 / 150
82 / 150
83 / 150
84 / 150
85 / 150
86 / 150
87 / 150
88 / 150
89 / 150
Question 90 of 150
A PM presents two schedule compression options to the sponsor. Option 1: Crash 5 critical activities (cost: $45,000, saves 12 days, low risk). Option 2: Fast-track 3 activity pairs (cost: $5,000, saves 12 days, medium-high risk with 40% chance of 8 days rework at $4,000/day). Which option should the PM recommend and why?
90 / 150
91 / 150
Question 92 of 150
A PM identifies that crashing Activity M saves 2 days at $3,000/day. However, crashing M causes a previously non-critical path to become critical. To maintain the 2-day savings, the PM must also crash Activity N on the new critical path at $2,500/day for 2 days. What is the true total cost of saving 2 days?
92 / 150
93 / 150
94 / 150
95 / 150
96 / 150
97 / 150
98 / 150
99 / 150
100 / 150
101 / 150
102 / 150
103 / 150
Question 104 of 150
A team's velocity over 8 sprints is: 20, 22, 24, 26, 28, 30, 32, 34. The PM notices a consistent upward trend. What does this pattern indicate and how should it affect planning?
104 / 150
105 / 150
106 / 150
107 / 150
108 / 150
109 / 150
110 / 150
111 / 150
112 / 150
113 / 150
114 / 150
115 / 150
116 / 150
117 / 150
118 / 150
119 / 150
120 / 150
121 / 150
122 / 150
123 / 150
124 / 150
125 / 150
126 / 150
127 / 150
128 / 150
129 / 150
130 / 150
131 / 150
132 / 150
133 / 150
134 / 150
135 / 150
136 / 150
137 / 150
138 / 150
139 / 150
140 / 150
141 / 150
142 / 150
143 / 150
144 / 150
145 / 150
146 / 150
147 / 150
148 / 150
149 / 150
Question 150 of 150
A PM reviews the complete schedule management approach for a large hybrid project. The approach includes: PDM network for infrastructure, CPM for critical path analysis, crashing/fast-tracking for compression, velocity-based sprint planning for software, release burnup for forecasting, and integrated milestone reporting. A senior stakeholder says this is too complex. How should the PM respond?
150 / 150