← Exams · PMP

PMBOK 7 - Schedule Management

Learning Objectives

Logic: Precedence Diagramming Method (PDM), Lead/Lag. Math: Critical Path, Total Float vs. Free Float. Agile: Sprint Mapping, Velocity, Release Planning.

Exams certification badge
Time left --:--:--
Question 1 / 150 · 150 unanswered
Question 1 of 150
A PM is sequencing project activities using the Precedence Diagramming Method (PDM). What does PDM use to represent activities and their logical relationships?
1 / 150
Question 2 of 150
In PDM, what are the four types of logical relationships between activities?
2 / 150
Question 3 of 150
Which dependency type is MOST commonly used in project scheduling and why?
3 / 150
Question 4 of 150
A PM has two activities: 'Pour concrete' and 'Cure concrete.' The curing must begin immediately when pouring finishes. What dependency type and what lead/lag should be applied?
4 / 150
Question 5 of 150
A PM uses a Start-to-Start (SS) relationship between 'Lay pipe' and 'Backfill trench.' The backfilling can begin 3 days after pipe laying starts. How is this modeled?
5 / 150
Question 6 of 150
What is the difference between lead time and lag time in PDM?
6 / 150
Question 7 of 150
A PM applies a 5-day lead to a Finish-to-Start relationship between Activity A (10 days) and Activity B. What does this mean for Activity B's start?
7 / 150
Question 8 of 150
A PM has a Finish-to-Start dependency between 'Submit document' and 'Receive approval.' The approval process takes a minimum of 10 business days. How should the PM model this waiting period?
8 / 150
Question 9 of 150
What is the difference between mandatory dependencies and discretionary dependencies in PDM?
9 / 150
Question 10 of 150
A PM identifies an external dependency on a government permit that must be obtained before construction begins. What type of dependency is this and how should it be managed?
10 / 150
Question 11 of 150
A PM draws a network diagram and discovers that Activity C has both a Finish-to-Start relationship with Activity A and a Start-to-Start relationship with Activity B. Activity A finishes on Day 10 and Activity B starts on Day 8. When is the EARLIEST Activity C can start?
11 / 150
Question 12 of 150
A PM uses a Finish-to-Finish (FF) relationship between 'Write code' and 'Write unit tests.' What does this mean operationally?
12 / 150
Question 13 of 150
A PM encounters the rarely-used Start-to-Finish (SF) dependency type. In which scenario would SF be MOST appropriate?
13 / 150
Question 14 of 150
A PM is building a network diagram for a software project. The testing team says they can begin writing test cases (Activity B) while requirements are still being finalized (Activity A), but they need at least 3 days of requirements work completed first. What is the best way to model this?
14 / 150
Question 15 of 150
A PM applies a 2-day lead to every FS relationship in the project to compress the schedule. What risk does this introduce?
15 / 150
Question 16 of 150
In a network diagram, a path goes: A(5d) -> B(3d) -> C(7d) -> D(4d). All relationships are FS with zero lag. What is the total duration of this path?
16 / 150
Question 17 of 150
A PM has Activity A (8 days) with an FS relationship to Activity B, but with a 3-day lag. If Activity A starts on Day 1 and finishes on Day 8, when does Activity B start?
17 / 150
Question 18 of 150
A PM modifies a Finish-to-Start relationship from FS + 0 lag to FS with a 5-day lead. How does this affect the network path duration?
18 / 150
Question 19 of 150
A PM creates a project schedule with 200 activities. During review, 15 activities have no predecessors and 12 activities have no successors. Besides the project start and end milestones, is this acceptable?
19 / 150
Question 20 of 150
A PM is evaluating whether to model a dependency as mandatory FS or discretionary SS to enable parallelism. What criteria should guide this decision?
20 / 150
Question 21 of 150
A network diagram shows: Activity X has an SS relationship with Activity Y (SS + 2-day lag), and Activity Y has an FF relationship with Activity Z (FF + 1-day lag). Activity X starts on Day 1 and has a duration of 10 days. Activity Y has a duration of 8 days. When does Activity Z finish at the EARLIEST?
21 / 150
Question 22 of 150
A PM identifies that painting interior walls (Activity B) can start 2 days before plastering (Activity A) finishes, because the plaster in earlier rooms will be dry by then. The PM models this as FS with a 2-day lead. A risk event occurs and plastering takes 5 extra days. How does this affect painting?
22 / 150
Question 23 of 150
A PM builds a network diagram and notices a circular dependency: Activity A depends on Activity B, which depends on Activity C, which depends on Activity A. What does this indicate?
23 / 150
Question 24 of 150
A PM has a project with 50 activities and needs to determine if the schedule can be compressed. The PM examines all discretionary dependencies. Why are discretionary dependencies specifically targeted for schedule compression?
24 / 150
Question 25 of 150
A PM presents a network diagram to the sponsor. The sponsor asks why some arrows are thicker than others. The PM explains that thick arrows represent the critical path. The sponsor then asks: 'What happens if we add a 15-day lag to a non-critical path activity?' What is the PM's BEST response?
25 / 150
Question 26 of 150
What is the critical path in a project network?
26 / 150
Question 27 of 150
A PM performs a forward pass through the network diagram. What does the forward pass calculate?
27 / 150
Question 28 of 150
A PM performs a backward pass through the network diagram. What does the backward pass calculate?
28 / 150
Question 29 of 150
Given the following network: A(3d) -> B(5d) -> D(4d) and A(3d) -> C(2d) -> D(4d). All FS with zero lag. What is the critical path and project duration?
29 / 150
Question 30 of 150
In a network with ES=5, EF=12, LS=8, LF=15 for Activity X, what is Activity X's total float?
30 / 150
Question 31 of 150
A project has the following network (all FS, zero lag): Start -> A(4) -> C(6) -> End; Start -> B(3) -> C(6) -> End; Start -> B(3) -> D(5) -> End. What is the critical path?
31 / 150
Question 32 of 150
During project execution, Activity E on the critical path is completed 2 days early. What happens to the project end date?
32 / 150
Question 33 of 150
Can a project have more than one critical path simultaneously?
33 / 150
Question 34 of 150
A PM calculates that the critical path is 60 working days. The sponsor requires project completion in 50 working days. What is the schedule variance?
34 / 150
Question 35 of 150
A PM performs a forward pass and calculates ES=0 for the first activity. At a merge point where Activity B (EF=10) and Activity C (EF=14) both feed into Activity D, what is Activity D's Early Start?
35 / 150
Question 36 of 150
During a backward pass, Activity E feeds into both Activity F (LS=20) and Activity G (LS=15). What is Activity E's Late Finish?
36 / 150
Question 37 of 150
A network has 6 paths. Path durations are: 22, 25, 25, 18, 20, 24 days. How many critical paths exist and what is the project duration?
37 / 150
Question 38 of 150
A PM identifies a 'near-critical path' with only 2 days of total float while the critical path has zero float. Why should the PM monitor this near-critical path?
38 / 150
Question 39 of 150
A PM calculates the critical path using CPM but does not consider resource constraints. The schedule shows a 40-day duration. After resource leveling, the duration extends to 52 days. What explains this increase?
39 / 150
Question 40 of 150
A PM uses the formula EF = ES + Duration - 1 in one schedule and EF = ES + Duration in another. Why might these differ?
40 / 150
Question 41 of 150
A network diagram has: A(3) -> B(4) -> E(2); A(3) -> C(6) -> E(2); D(5) -> E(2). All FS, zero lag. What is the critical path?
41 / 150
Question 42 of 150
A PM presents the critical path analysis to the team. A team member asks: 'Does the critical path ever change during the project?' What is the correct answer?
42 / 150
Question 43 of 150
A project has three parallel paths merging into a final activity. Path A = 20 days (critical), Path B = 18 days (2 days float), Path C = 15 days (5 days float). A risk event adds 4 days to Path B. What happens?
43 / 150
Question 44 of 150
A PM is asked to calculate the Early Start (ES) for Activity H. Activity H has three predecessors: E (EF=12), F (EF=15), G (EF=9). All are FS with zero lag. What is H's ES?
44 / 150
Question 45 of 150
After performing forward and backward passes, a PM finds that Activity J has ES=10, EF=16, LS=10, LF=16. What can be concluded about Activity J?
45 / 150
Question 46 of 150
A PM calculates that Activity K has a total float of -3 days. What does negative float indicate?
46 / 150
Question 47 of 150
A PM uses the Critical Path Method on a project with high uncertainty in activity durations. A colleague suggests using PERT instead. What advantage does PERT offer over CPM for uncertain durations?
47 / 150
Question 48 of 150
Using PERT, an activity has optimistic duration = 4 days, most likely = 7 days, pessimistic = 16 days. What is the PERT expected duration?
48 / 150
Question 49 of 150
Using PERT, the critical path has a total expected duration of 50 days with a path standard deviation of 5 days. What is the probability that the project will finish in 55 days or less?
49 / 150
Question 50 of 150
A PM creates a schedule with 12 activities. After CPM analysis, only 3 activities are on the critical path. The sponsor says: 'Since 9 activities are non-critical, we can cut their resources.' Why is this a risky approach?
50 / 150
Question 51 of 150
A PM is asked to crash the project schedule. Activity L is on the critical path with a normal duration of 10 days (cost $5,000) and a crash duration of 7 days (cost $8,000). What is the crash cost per day?
51 / 150
Question 52 of 150
A PM must reduce the project duration by 5 days. Three critical path activities can be crashed: X (cost $800/day, max 3 days), Y (cost $1,200/day, max 4 days), Z (cost $600/day, max 2 days). What is the optimal crashing sequence?
52 / 150
Question 53 of 150
After crashing Activity Z by 2 days on the critical path, the PM recalculates the network and discovers that a previously non-critical path is now the critical path. What should the PM do?
53 / 150
Question 54 of 150
What is the difference between crashing and fast-tracking as schedule compression techniques?
54 / 150
Question 55 of 150
A PM fast-tracks two critical path activities by changing their FS relationship to SS with a 3-day lag. The activities originally had a combined sequential duration of 20 days (Activity M = 8 days, Activity N = 12 days). What is the new combined duration for this portion of the path?
55 / 150
Question 56 of 150
What is the fundamental difference between Total Float and Free Float?
56 / 150
Question 57 of 150
How is Free Float calculated for an activity?
57 / 150
Question 58 of 150
Activity P has ES=5, EF=12, LS=9, LF=16. Its only successor Activity Q has ES=15. What are Activity P's Total Float and Free Float?
58 / 150
Question 59 of 150
On a non-critical path, three sequential activities each have Total Float = 8 days. A team member assumes each activity can be independently delayed by 8 days. Why is this assumption incorrect?
59 / 150
Question 60 of 150
Why is Free Float particularly important for resource scheduling decisions?
60 / 150
Question 61 of 150
A network has: A(4) -> C(3) and B(6) -> C(3). A starts Day 1, B starts Day 1. What is Activity A's Free Float?
61 / 150
Question 62 of 150
In the same network as the previous question, if Activity A has Total Float = 2 days and Free Float = 2 days, what does it mean when TF equals FF?
62 / 150
Question 63 of 150
Can an activity on the critical path have Free Float greater than zero?
63 / 150
Question 64 of 150
A PM analyzes the schedule and finds Activity R with TF = 10 days and FF = 0 days. What does this tell the PM about Activity R's position in the network?
64 / 150
Question 65 of 150
A PM is resource leveling and needs to delay one of two parallel activities. Activity S has TF=5, FF=5. Activity T has TF=5, FF=0. Which activity should the PM delay and why?
65 / 150
Question 66 of 150
What is 'Project Float' (also called Project Buffer or Project Slack)?
66 / 150
Question 67 of 150
A PM uses Critical Chain Method (CCM) instead of traditional CPM. How does CCM handle float differently?
67 / 150
Question 68 of 150
In Critical Chain scheduling, what is a 'feeding buffer' and where is it placed?
68 / 150
Question 69 of 150
Activity U has TF = 6 and FF = 4. If Activity U is delayed by 5 days, what is the impact?
69 / 150
Question 70 of 150
A schedule shows Path 1 (critical): A(5)-B(8)-C(6) = 19 days. Path 2: D(4)-E(3)-C(6) = 13 days. What is the Total Float and Free Float for Activity D?
70 / 150
Question 71 of 150
In the same network, what is Activity E's Free Float?
71 / 150
Question 72 of 150
A PM notices that the last activity before a merge point on a non-critical path often has the highest Free Float. Why is this?
72 / 150
Question 73 of 150
A PM uses a scheduling tool that shows a 'float histogram' — a bar chart showing the distribution of float across all activities. Most activities have zero float, and a few have large float values. What does this distribution suggest about the schedule?
73 / 150
Question 74 of 150
A team lead asks: 'If I start my activity on its Late Start date instead of its Early Start date, what happens to its float?' How should the PM respond?
74 / 150
Question 75 of 150
A PM calculates float for all activities but forgets to account for a 5-day lag on one FS relationship. How does adding this lag affect float calculations?
75 / 150
Question 76 of 150
A PM applies resource leveling to the schedule. Before leveling, Activity V had TF=8 and FF=3. After leveling, Activity V is delayed to resolve a resource conflict. How are Activity V's float values affected?
76 / 150
Question 77 of 150
A schedule baseline shows 45 activities. Of these, 12 are on the critical path (zero float), 8 have TF between 1-5 days, 15 have TF between 6-15 days, and 10 have TF > 15 days. The PM wants to assign a schedule risk rating. Which metric provides the best risk indicator?
77 / 150
Question 78 of 150
A PM reports that the project's 'schedule sensitivity index' for a particular path is 0.85. What does this mean?
78 / 150
Question 79 of 150
A PM is explaining float to a non-technical sponsor. The sponsor asks: 'If we have 10 days of float on Activity W, can we reassign Activity W's resources to another project for 10 days and then bring them back?' What should the PM advise?
79 / 150
Question 80 of 150
A project has Activities A(5), B(3), C(7), D(4). Dependencies: A->C, B->C, C->D. All FS zero lag. What is Activity B's Total Float and Free Float?
80 / 150
Question 81 of 150
A PM needs to reduce the project schedule by 8 days. The critical path has 5 activities. After crashing the cheapest critical activity to its maximum (saving 4 days), the PM recalculates and finds two paths are now tied as critical. What must the PM do to save the remaining 4 days?
81 / 150
Question 82 of 150
A PM evaluates crashing options. Activity A: crash cost $500/day, max 3 days, on critical path. Activity B: crash cost $400/day, max 5 days, NOT on critical path (has 2 days float). What should the PM crash?
82 / 150
Question 83 of 150
A PM fast-tracks two critical path activities by overlapping them. The original sequence was: Design (20 days) -> Build (15 days) = 35 days total. After fast-tracking with SS + 10-day lag, what is the new duration and what risk is introduced?
83 / 150
Question 84 of 150
A PM considers both crashing and fast-tracking for the same critical path segment. Crashing would cost $15,000 to save 5 days. Fast-tracking would save the same 5 days at no direct cost but introduces a 30% probability of 10 days of rework. Which option has a lower expected cost?
84 / 150
Question 85 of 150
A PM has exhausted all crashing options on the critical path (all activities are at their crash duration). The schedule is still 3 days too long. What options remain?
85 / 150
Question 86 of 150
A PM fast-tracks the project by starting Phase 2 before Phase 1 is complete. Six weeks later, a Phase 1 deliverable is rejected, requiring Phase 2 work to be partially redone. What type of risk did the PM fail to adequately manage?
86 / 150
Question 87 of 150
A PM applies crashing to Activity X, adding 3 extra team members. Activity X's duration decreases from 10 days to 7 days. However, the PM notices that communication overhead has increased. What principle explains why adding resources does not produce proportional time savings?
87 / 150
Question 88 of 150
A PM needs to decide between crashing Activity Y at $2,000/day and crashing Activity Z at $3,000/day. Both are on the critical path and can each be crashed by up to 3 days. The PM needs to save 3 days. Which approach minimizes cost?
88 / 150
Question 89 of 150
A PM considers fast-tracking by changing a Finish-to-Start relationship to Start-to-Start. The predecessor activity has a high degree of design uncertainty. Why should the PM be cautious about fast-tracking in this situation?
89 / 150
Question 90 of 150
A PM presents two schedule compression options to the sponsor. Option 1: Crash 5 critical activities (cost: $45,000, saves 12 days, low risk). Option 2: Fast-track 3 activity pairs (cost: $5,000, saves 12 days, medium-high risk with 40% chance of 8 days rework at $4,000/day). Which option should the PM recommend and why?
90 / 150
Question 91 of 150
A PM uses resource leveling and discovers that it extends the critical path from 40 to 48 days. The sponsor refuses to accept the 8-day extension. What technique can the PM use to compress the resource-leveled schedule without adding cost?
91 / 150
Question 92 of 150
A PM identifies that crashing Activity M saves 2 days at $3,000/day. However, crashing M causes a previously non-critical path to become critical. To maintain the 2-day savings, the PM must also crash Activity N on the new critical path at $2,500/day for 2 days. What is the true total cost of saving 2 days?
92 / 150
Question 93 of 150
A PM applies fast-tracking and crashing simultaneously to different portions of the critical path. Fast-tracking saves 6 days on one segment while crashing saves 4 days on another. Can the PM claim a total schedule reduction of 10 days?
93 / 150
Question 94 of 150
A PM fast-tracks by converting mandatory FS dependencies to SS. A quality auditor flags this as a violation. Why is the auditor concerned?
94 / 150
Question 95 of 150
A PM uses schedule compression to meet a deadline. After crashing and fast-tracking, the project schedule meets the target but with 15% less total float than the original baseline. What should the PM communicate to stakeholders?
95 / 150
Question 96 of 150
A construction PM uses a technique called 'schedule compression by substitution.' Instead of crashing or fast-tracking, the PM replaces a 15-day concrete curing process with a rapid-cure concrete that takes 5 days. What type of compression is this?
96 / 150
Question 97 of 150
A PM has compressed the schedule as much as possible but the critical path is still 5 days too long. All crashing options are exhausted, fast-tracking is too risky, and scope cannot be reduced. What negotiation strategy should the PM use with the sponsor?
97 / 150
Question 98 of 150
A PM is evaluating whether to fast-track 'System Integration Testing' by starting it before 'Unit Testing' is complete. 80% of modules have passed unit testing but 20% are still being tested. What factor is MOST critical in this fast-tracking decision?
98 / 150
Question 99 of 150
A PM applies schedule compression iteratively. In round 1, crashing saves 3 days at $2,000/day. In round 2, crashing saves 2 more days but at $4,500/day (because cheaper options were exhausted and a new critical path emerged). What trend does this illustrate?
99 / 150
Question 100 of 150
A PM is asked to create a 'time-cost trade-off curve' for the project. What does this curve show and how is it used?
100 / 150
Question 101 of 150
What is velocity in agile project management and how is it measured?
101 / 150
Question 102 of 150
A team completes the following story points over 5 sprints: 28, 32, 25, 35, 30. What is the team's average velocity and how should the PM use this for planning?
102 / 150
Question 103 of 150
A newly formed team has no historical velocity data. They are about to start their first sprint with a 2-week timebox. How should the PM estimate the first sprint's capacity?
103 / 150
Question 104 of 150
A team's velocity over 8 sprints is: 20, 22, 24, 26, 28, 30, 32, 34. The PM notices a consistent upward trend. What does this pattern indicate and how should it affect planning?
104 / 150
Question 105 of 150
A Scrum team has a velocity of 25 story points per sprint. During sprint planning, the product owner wants the team to commit to 35 points because there is a critical release deadline. What should the team do?
105 / 150
Question 106 of 150
A team's velocity drops from 30 to 18 over two sprints. What should the Scrum Master investigate?
106 / 150
Question 107 of 150
Management wants to compare velocity between Team A (velocity 40) and Team B (velocity 25) to determine which team is more productive. Why is this comparison invalid?
107 / 150
Question 108 of 150
What is a sprint burndown chart and what does it show?
108 / 150
Question 109 of 150
A sprint burndown chart shows the actual line flat for the first 5 days, then dropping sharply on days 6-10. What pattern does this indicate?
109 / 150
Question 110 of 150
What is the difference between a sprint burndown chart and a release burnup chart?
110 / 150
Question 111 of 150
A team has a velocity of 20 points per sprint. The release backlog has 100 story points. Using velocity-based forecasting, when will the release be ready?
111 / 150
Question 112 of 150
A team uses sprint mapping to plan a 6-sprint release. They allocate Sprint 1-2 for architecture and infrastructure stories, Sprint 3-5 for feature stories, and Sprint 6 for hardening and bug fixes. What concern should the Scrum Master raise about this plan?
112 / 150
Question 113 of 150
A team's velocity for the last 6 sprints is: 22, 28, 18, 30, 24, 26. The PM calculates an average of 24.7. A team member says the average is misleading because of the high variance. What additional metric should the PM provide?
113 / 150
Question 114 of 150
A Scrum team uses 'yesterday's weather' to plan sprint capacity. What does this mean?
114 / 150
Question 115 of 150
A team finishes a sprint with 5 of 7 committed stories done (velocity = 24 points out of 35 committed). Two stories (11 points) are 80% complete. Should the PM count partial credit toward velocity?
115 / 150
Question 116 of 150
A PM asks the team to increase velocity by 20% for the next quarter. How should the Scrum Master respond to this request?
116 / 150
Question 117 of 150
What is a sprint goal and how does it relate to sprint planning and velocity?
117 / 150
Question 118 of 150
A team uses Kanban instead of Scrum. They do not have fixed sprints. How do they measure and forecast delivery without velocity?
118 / 150
Question 119 of 150
A team has a velocity of 30 points per 2-week sprint. Management asks the PM to convert this to a traditional schedule (weeks). How should the PM translate agile velocity into a timeline for a 180-point release?
119 / 150
Question 120 of 150
A team tracks both velocity (story points completed) and throughput (stories completed). Velocity is stable at 30 points/sprint but throughput dropped from 8 stories to 4 stories per sprint. What does this discrepancy indicate?
120 / 150
Question 121 of 150
A PM creates a 'sprint mapping' view that shows which features will be delivered in which sprints over the next 4 sprints. A stakeholder treats this as a commitment. What should the PM clarify?
121 / 150
Question 122 of 150
A team uses 'capacity-based sprint planning' instead of velocity-based planning. How does capacity-based planning work?
122 / 150
Question 123 of 150
A Scrum team has a WIP (Work In Progress) limit of 3 for the 'In Development' column on their board. Currently, 3 stories are in development and a developer finishes one. Instead of pulling a new story, they help another developer with a struggling story. Why is this behavior encouraged?
123 / 150
Question 124 of 150
A team uses story points but a new developer says they are 'just guessing.' How should the Scrum Master explain the purpose and method of story point estimation?
124 / 150
Question 125 of 150
A PM tracks the team's velocity trend and notices it has stabilized around 25 points per sprint for the last 8 sprints. The team suggests they should stop tracking velocity since it does not change. What is the PM's best response?
125 / 150
Question 126 of 150
What is release planning in agile and how does it differ from sprint planning?
126 / 150
Question 127 of 150
A PM uses two approaches to release planning: date-driven and feature-driven. What is the difference?
127 / 150
Question 128 of 150
A PM creates a release plan showing 8 sprints to complete 200 story points (velocity = 25/sprint). After Sprint 3, velocity is averaging 22 and the backlog has grown to 220 points (20 points added). What is the revised release forecast?
128 / 150
Question 129 of 150
A PM is managing a hybrid project where the backend (predictive) uses a CPM schedule and the frontend (agile) uses sprints and velocity. A backend activity on the critical path is a predecessor to frontend Sprint 4 work. How should the PM manage this cross-methodology dependency?
129 / 150
Question 130 of 150
A PM uses Monte Carlo simulation for release forecasting. After 10,000 simulations using historical velocity data, the results show: 50th percentile = Sprint 8, 85th percentile = Sprint 10, 95th percentile = Sprint 12. What should the PM communicate to stakeholders?
130 / 150
Question 131 of 150
A team uses the 'Program Increment (PI) Planning' ceremony from SAFe. How does PI Planning relate to traditional release planning and sprint mapping?
131 / 150
Question 132 of 150
A PM manages a project with a fixed delivery date (immovable external deadline) and a prioritized backlog of 150 story points. The team's velocity is 25 points/sprint with 2-week sprints. There are 5 sprints until the deadline. What should the PM communicate to the product owner?
132 / 150
Question 133 of 150
A PM uses a 'cumulative flow diagram' (CFD) to monitor schedule health in a Kanban/agile context. What does the CFD show and what patterns indicate schedule risk?
133 / 150
Question 134 of 150
A PM is asked to create a 'schedule baseline' for a project that uses both CPM (for infrastructure) and agile sprints (for software). What should this hybrid schedule baseline include?
134 / 150
Question 135 of 150
A PM notices that the project's SPI (Schedule Performance Index) is 0.9 and the agile team's velocity trend is declining. Both metrics suggest the project is falling behind. The PM decides to fast-track the CPM portion and add capacity to the agile team. What should the PM verify FIRST?
135 / 150
Question 136 of 150
A PM builds a project schedule and identifies 4 paths with durations of 45, 42, 44, and 38 days. The project deadline is 46 days. What is the project float and which paths require monitoring?
136 / 150
Question 137 of 150
A PM schedules a project using CPM and establishes the baseline. During execution, a stakeholder asks: 'What is the difference between the schedule baseline, the schedule model, and the project schedule?' How should the PM explain?
137 / 150
Question 138 of 150
A team is transitioning from waterfall to agile. They previously used detailed Gantt charts with 500 tasks. Management still wants to see Gantt-style reporting. How can the PM bridge both worlds?
138 / 150
Question 139 of 150
A project has a critical path of A(5)->B(8)->C(6)->D(4) = 23 days. The PM identifies a risk that Activity B may take 12 days instead of 8 (50% probability). Using expected value analysis, what is the expected project duration?
139 / 150
Question 140 of 150
A PM needs to report schedule status to different audiences: the team, the sponsor, and the steering committee. What schedule visualization should each audience receive?
140 / 150
Question 141 of 150
A PM identifies that 3 activities on the critical path can each be performed by one of two resources: a senior (costs $200/hr, works 50% faster) or a junior ($100/hr, normal speed). The critical path is 30 days. Using the senior resource for all 3 activities would reduce the critical path to 25 days. What analysis should the PM perform?
141 / 150
Question 142 of 150
A PM uses the 'Schedule Risk Assessment' technique and identifies that Activity E (critical path, 15-day duration) has no float, high complexity, a single-point-of-failure resource, and an external dependency. What risk response should the PM implement?
142 / 150
Question 143 of 150
A project schedule shows 150 activities. The PM runs a schedule quality check and finds: 12 activities have no predecessors (excluding the start milestone), 8 activities have no successors (excluding the finish milestone), and 20 activities have only FS+0 relationships with over 30 days duration. What schedule quality issues exist?
143 / 150
Question 144 of 150
A PM uses 'schedule reserves' in the project schedule. What are the two types of schedule reserves and who controls each?
144 / 150
Question 145 of 150
A team completes Sprint 5 and the release burnup chart shows 120 points completed with 80 points remaining. Average velocity is 24 points/sprint. But the product owner just added 20 new points to the backlog. What does the updated release forecast show?
145 / 150
Question 146 of 150
A PM uses lead time and cycle time metrics from Kanban to forecast delivery. The team's average cycle time is 4 days per story with a standard deviation of 2 days. A stakeholder needs 10 stories completed. What is a reasonable forecast?
146 / 150
Question 147 of 150
A PM manages a project with 3 phases. Phase 1 uses agile (8 sprints), Phase 2 uses predictive CPM (45 days), and Phase 3 uses agile (4 sprints). Sprints are 2 weeks. What is the estimated project timeline?
147 / 150
Question 148 of 150
A PM presents a schedule to the sponsor that shows the project finishing 2 weeks early. The sponsor asks the PM to add those 2 weeks as buffer. Where should this buffer be placed in the schedule?
148 / 150
Question 149 of 150
A PM is asked: 'Which is better for schedule management — CPM or agile sprints?' What is the most accurate answer from a PMBOK 7 perspective?
149 / 150
Question 150 of 150
A PM reviews the complete schedule management approach for a large hybrid project. The approach includes: PDM network for infrastructure, CPM for critical path analysis, crashing/fast-tracking for compression, velocity-based sprint planning for software, release burnup for forecasting, and integrated milestone reporting. A senior stakeholder says this is too complex. How should the PM respond?
150 / 150