← Exams · PMP

PMBOK 7 - Stakeholders & Comms

Learning Objectives

Stakeholders: Power/Interest Grid, Salience Model, Stakeholder Cube, Engagement Assessment Matrix. Comms: Communication models, noise, push/pull/interactive methods.

Exams certification badge
Time left --:--:--
Question 1 / 150 · 150 unanswered
Question 1 of 150
A project manager identifies a government regulator who has HIGH power to shut down the project but LOW interest in day-to-day activities. Using the Power/Interest Grid, which quadrant does this stakeholder fall into and what is the recommended engagement strategy?
1 / 150
Question 2 of 150
During stakeholder analysis, the PM places the project sponsor in the High Power / High Interest quadrant. Three months into execution, the sponsor delegates project oversight to a deputy and becomes disengaged. How should the PM adjust the engagement strategy?
2 / 150
Question 3 of 150
A junior developer on the project team has LOW power but is extremely vocal about design decisions and actively lobbies other team members (HIGH interest). Using the Power/Interest Grid, what is the recommended strategy?
3 / 150
Question 4 of 150
The Power/Interest Grid reveals that 70% of identified stakeholders fall in the Low Power / Low Interest quadrant. A team member suggests removing them from the stakeholder register to reduce overhead. What is the PM's BEST response?
4 / 150
Question 5 of 150
A PM is presenting the Power/Interest Grid to the project team. A team member asks whether the grid should be shared with all stakeholders. What is the BEST guidance?
5 / 150
Question 6 of 150
Two stakeholders have conflicting interests. The CFO (High Power / High Interest) wants to minimize project costs, while the VP of Quality (High Power / High Interest) demands premium materials. Both are in the 'Manage Closely' quadrant. How should the PM handle this?
6 / 150
Question 7 of 150
A stakeholder initially classified as Low Power / Low Interest files a formal complaint with senior management about the project's environmental impact. This complaint gains media attention. How should the PM respond?
7 / 150
Question 8 of 150
A PM is using the Power/Interest Grid for a large infrastructure project with 200+ stakeholders. The grid becomes unwieldy with too many data points. What is the MOST effective approach?
8 / 150
Question 9 of 150
The Power/Interest Grid shows that the project's end users are High Interest / Low Power. The PM allocates minimal engagement effort since they have low power. What risk does this create?
9 / 150
Question 10 of 150
A PM discovers that a stakeholder has been deliberately misrepresenting their interest level — publicly appearing disinterested while privately lobbying against the project. How does this affect the Power/Interest Grid analysis?
10 / 150
Question 11 of 150
In an agile project, the product owner is classified as High Power / High Interest. The Scrum Master notices the product owner is making all decisions without consulting the development team. What should the Scrum Master address?
11 / 150
Question 12 of 150
A PM needs to decide how to allocate limited stakeholder engagement budget. The Power/Interest Grid shows 5 stakeholders in Manage Closely, 12 in Keep Satisfied, 25 in Keep Informed, and 60 in Monitor. How should the budget be distributed?
12 / 150
Question 13 of 150
A new executive joins the organization midway through the project. The PM has no information about their power level or interest. Where should the PM tentatively place this stakeholder on the Power/Interest Grid?
13 / 150
Question 14 of 150
The Power/Interest Grid is ONE tool for stakeholder classification. What is its PRIMARY limitation compared to more advanced models?
14 / 150
Question 15 of 150
A PM classifies a labor union as High Power / High Interest on the Power/Interest Grid. The union has the power to halt construction through strikes. What engagement approach goes BEYOND the standard 'Manage Closely' recommendation?
15 / 150
Question 16 of 150
A project has both internal and external stakeholders mapped on the Power/Interest Grid. The PM notices that all external stakeholders are placed in the bottom two quadrants (low power). A senior team member warns this may be a mistake. Why?
16 / 150
Question 17 of 150
A PM updates the Power/Interest Grid quarterly. Between updates, a key stakeholder's department is reorganized, shifting their authority. The PM does not learn of this until the next quarterly review. What process improvement should be implemented?
17 / 150
Question 18 of 150
A PM is working in a matrix organization where functional managers have significant influence. Three functional managers are classified as High Power / Medium Interest. What specific risk does the matrix structure create for stakeholder management?
18 / 150
Question 19 of 150
A virtual project team spans 4 countries. The PM creates a Power/Interest Grid and notices that stakeholders in the headquarters country are rated higher in power than equally positioned stakeholders in other countries. What bias should the PM check for?
19 / 150
Question 20 of 150
The PM creates a Power/Interest Grid at project initiation and a comprehensive stakeholder engagement plan based on it. At the end of the project, a lessons learned review reveals that several key stakeholder relationships were poorly managed. What is the MOST likely root cause?
20 / 150
Question 21 of 150
The Salience Model classifies stakeholders based on three attributes. What are these three attributes?
21 / 150
Question 22 of 150
In the Salience Model, a stakeholder who possesses Power AND Legitimacy but NOT Urgency is classified as what type?
22 / 150
Question 23 of 150
A stakeholder has Urgency (they need something NOW) but lacks both Power and Legitimacy. In the Salience Model, they are classified as a 'Demanding' stakeholder. How should the PM manage them?
23 / 150
Question 24 of 150
A stakeholder possesses ALL THREE attributes — Power, Legitimacy, and Urgency. In the Salience Model, what is this classification and what does it mean for the PM?
24 / 150
Question 25 of 150
A community group near the project site has Legitimacy (the project directly affects them) and Urgency (construction begins next week) but no formal Power. The Salience Model classifies them as 'Dependent.' What does this mean?
25 / 150
Question 26 of 150
A wealthy investor in the parent company has significant Power but no Legitimacy (they are not connected to the project) and no Urgency. The Salience Model classifies them as 'Dormant.' Why should the PM still monitor them?
26 / 150
Question 27 of 150
What is the KEY advantage of the Salience Model over the Power/Interest Grid?
27 / 150
Question 28 of 150
A PM is using the Salience Model and struggles to assess 'Legitimacy' for a stakeholder. What criteria should be used to determine if a stakeholder has legitimacy?
28 / 150
Question 29 of 150
A stakeholder has Power and Urgency but no Legitimacy. The Salience Model classifies them as 'Dangerous.' Why is this classification appropriate?
29 / 150
Question 30 of 150
A PM classifies a stakeholder as 'Discretionary' (Legitimacy only, no Power or Urgency). What is the typical engagement approach for discretionary stakeholders?
30 / 150
Question 31 of 150
During a project phase transition, several stakeholders gain urgency as deadlines approach. How does this affect the Salience Model classification?
31 / 150
Question 32 of 150
A PM uses both the Power/Interest Grid and the Salience Model for the same project. The Power/Interest Grid shows a stakeholder as High Power / Low Interest. The Salience Model shows them as Dormant (Power only). Are these classifications consistent?
32 / 150
Question 33 of 150
An organization mandates the use of the Salience Model for all projects. A PM on a small, 3-month project with 8 stakeholders finds the model overly complex. What should the PM recommend?
33 / 150
Question 34 of 150
In the Salience Model, how many distinct stakeholder classes exist for those possessing at least one attribute?
34 / 150
Question 35 of 150
A PM is debating whether to use the Salience Model or the Power/Interest Grid. What is the BEST guidance for choosing between these tools?
35 / 150
Question 36 of 150
The Stakeholder Cube extends stakeholder analysis beyond two dimensions. What does it add compared to the Power/Interest Grid?
36 / 150
Question 37 of 150
A PM uses the Stakeholder Cube and identifies a stakeholder with High Power, High Interest, and a Resistant attitude. What engagement strategy is MOST appropriate?
37 / 150
Question 38 of 150
When does the Stakeholder Cube provide MORE value than the Power/Interest Grid?
38 / 150
Question 39 of 150
A PM maps stakeholders on a Stakeholder Cube and finds that most stakeholders are clustered as Low Power / Low Interest / Neutral. The PM concludes stakeholder management will be minimal. What is the flaw in this reasoning?
39 / 150
Question 40 of 150
A PM wants to convert a key stakeholder from 'Resistant' to 'Supportive' on the Stakeholder Cube. What approach does PMBOK 7 recommend?
40 / 150
Question 41 of 150
The Stakeholder Cube reveals that the attitude dimension shows 5 supportive, 3 neutral, and 2 resistant stakeholders in the High Power group. The PM focuses all energy on the 2 resistant stakeholders. What risk does this create?
41 / 150
Question 42 of 150
A PM wants to visualize the Stakeholder Cube analysis for the team but finds a literal 3D cube diagram confusing. What is a practical alternative for presenting three-dimensional stakeholder data?
42 / 150
Question 43 of 150
In the Stakeholder Cube, what happens when a previously Supportive, High Power stakeholder's attitude shifts to Resistant due to a scope change that negatively affects their department?
43 / 150
Question 44 of 150
A PM is using the Stakeholder Cube for an organizational change project. Many stakeholders are classified as 'Resistant' because the project threatens their current roles. What cross-functional plan should the PM develop?
44 / 150
Question 45 of 150
A PM debates whether to use the Stakeholder Cube, the Salience Model, or the Power/Interest Grid. The project involves significant organizational change with strong political dynamics. Which tool combination would be MOST effective?
45 / 150
Question 46 of 150
What is the PRIMARY purpose of the Stakeholder Engagement Assessment Matrix?
46 / 150
Question 47 of 150
The Stakeholder Engagement Assessment Matrix uses five engagement levels. What are they?
47 / 150
Question 48 of 150
A stakeholder is currently at 'Resistant' (C) and the desired level is 'Supportive' (D). This represents a TWO-LEVEL gap. What does this imply for the PM's engagement effort?
48 / 150
Question 49 of 150
For a particular stakeholder, the current engagement is 'Supportive' (C) and the desired engagement is also 'Supportive' (D). Does the PM need to take any action?
49 / 150
Question 50 of 150
The PM creates an Engagement Assessment Matrix showing the project sponsor is currently 'Neutral' (C) when the desired level is 'Leading' (D). This is the widest gap on the matrix. What should the PM prioritize?
50 / 150
Question 51 of 150
How frequently should the Stakeholder Engagement Assessment Matrix be reviewed and updated?
51 / 150
Question 52 of 150
A PM is using the Engagement Assessment Matrix and discovers that 8 out of 10 key stakeholders need to move from their current engagement level to a higher desired level. Resources are limited. How should the PM prioritize engagement efforts?
52 / 150
Question 53 of 150
A stakeholder's current engagement is 'Unaware' and the desired level is 'Supportive.' The PM sends one introductory email and marks the engagement action as complete. Is this sufficient?
53 / 150
Question 54 of 150
The Engagement Assessment Matrix for an agile project shows the development team is currently 'Supportive' but the desired level is 'Leading.' What actions would move them from Supportive to Leading?
54 / 150
Question 55 of 150
A PM detects that a previously 'Supportive' stakeholder has shifted to 'Resistant' between two matrix reviews. What should the PM do FIRST?
55 / 150
Question 56 of 150
The Engagement Assessment Matrix is a sensitive document. Who should have access to it?
56 / 150
Question 57 of 150
A PM tracks engagement levels over time using successive Engagement Assessment Matrix snapshots. This trend analysis shows stakeholder engagement generally declining over the past 3 months. What does this signal?
57 / 150
Question 58 of 150
A PM is determining the 'desired' engagement level for each stakeholder. Who should participate in setting these desired levels?
58 / 150
Question 59 of 150
The Engagement Assessment Matrix shows that the end-user community is currently 'Unaware' with a desired level of 'Supportive.' The PM has 12 months until the system goes live. What phased engagement approach is MOST effective?
59 / 150
Question 60 of 150
A PM completes the Engagement Assessment Matrix and creates action plans for each gap. After 2 months, no actions have been executed due to competing priorities. What organizational issue does this reveal?
60 / 150
Question 61 of 150
According to PMBOK 7, when should stakeholder identification begin?
61 / 150
Question 62 of 150
A PM identifies 50 stakeholders at initiation. By the end of the project, the stakeholder register contains 120 entries. What does this growth indicate?
62 / 150
Question 63 of 150
A PM uses interviews, questionnaires, and brainstorming to identify stakeholders. A senior team member suggests 'stakeholder mapping workshops' as an additional technique. What is the advantage of this approach?
63 / 150
Question 64 of 150
The stakeholder register is a KEY output of stakeholder identification. What information should it contain beyond names and contact details?
64 / 150
Question 65 of 150
A PM has identified a stakeholder who is strongly opposed to the project. The PM considers excluding them from the stakeholder register to avoid complications. What is wrong with this approach?
65 / 150
Question 66 of 150
PMBOK 7 identifies 'Stakeholders' as one of its eight performance domains. What is the CORE focus of this performance domain?
66 / 150
Question 67 of 150
A project affects multiple organizational departments differently — some benefit, some face disruption. The PM applies the same engagement strategy to all departments. What principle does this violate?
67 / 150
Question 68 of 150
A PM notices increasing resistance from middle managers who were initially neutral. Investigation reveals they were never consulted about how the project would change their reporting processes. What stakeholder engagement principle was violated?
68 / 150
Question 69 of 150
The PM identifies that a key stakeholder is influenced by two other stakeholders — whatever they support, the key stakeholder tends to follow. How should the PM use this knowledge?
69 / 150
Question 70 of 150
A virtual project team has stakeholders in 5 different time zones with 3 different languages. What is the MOST significant stakeholder engagement challenge?
70 / 150
Question 71 of 150
A project is in its closing phase. The PM discovers stakeholders who were never identified during the project but were affected by the deliverables. What should the PM document in lessons learned?
71 / 150
Question 72 of 150
A PM is using the Stakeholder performance domain from PMBOK 7. The domain references 'checking outcomes.' What outcomes indicate effective stakeholder engagement?
72 / 150
Question 73 of 150
A PM manages a project where the sponsor is disengaged and stakeholders frequently bypass the PM to make requests directly to team members. What foundational stakeholder management issue does this indicate?
73 / 150
Question 74 of 150
A stakeholder analysis reveals that a vendor's project manager has significant informal influence over the client's decision-makers through personal relationships. This informal influence is not reflected in the organizational chart. How should the PM account for this?
74 / 150
Question 75 of 150
The PM identifies 15 stakeholders who will be negatively impacted by the project's outcome (job displacement due to automation). How should the PM address their needs according to PMBOK 7?
75 / 150
Question 76 of 150
During stakeholder engagement, the PM learns that different stakeholders have contradictory expectations for the project deliverables. The marketing department expects a customer-facing focus, while the operations department expects internal efficiency. How should the PM resolve this?
76 / 150
Question 77 of 150
A PM is managing stakeholder expectations for an agile project. A key stakeholder expects fixed scope delivered by a fixed date, which contradicts agile's flexible scope approach. What should the PM do?
77 / 150
Question 78 of 150
A PM asks stakeholders to complete satisfaction surveys after each major milestone. Response rates are below 10%. What is the MOST likely cause and remedy?
78 / 150
Question 79 of 150
The PMBOK 7 Stakeholder performance domain mentions the concept of 'stakeholder satisfaction.' How does this differ from 'stakeholder agreement'?
79 / 150
Question 80 of 150
A PM inherits a project from a predecessor who had poor stakeholder relationships. Multiple key stakeholders are disengaged or hostile. What should the PM do FIRST?
80 / 150
Question 81 of 150
In the basic communication model, what are the five key components?
81 / 150
Question 82 of 150
A PM sends a detailed technical email about a critical architecture decision to the project sponsor (a non-technical executive). The sponsor responds with an unrelated question. What communication model concept explains this failure?
82 / 150
Question 83 of 150
'Noise' in the communication model can be physical, psychological, or semantic. A PM holds a project meeting in a noisy construction area. Team members miss key points. What type of noise is this?
83 / 150
Question 84 of 150
A team member has just learned that their department may be restructured. During a project planning meeting, they appear distracted and miss important assignments. What type of communication noise is affecting them?
84 / 150
Question 85 of 150
A PM uses the term 'sprint' in a status report to a traditional manufacturing stakeholder group. They interpret 'sprint' as 'rush the work' rather than the agile meaning of a time-boxed iteration. What type of noise caused this misunderstanding?
85 / 150
Question 86 of 150
The communication model includes 'feedback' as a critical component. A PM presents a project update and asks 'Any questions?' The room is silent. Should the PM assume the message was received and understood?
86 / 150
Question 87 of 150
A PM communicates a project delay to stakeholders via email. Some stakeholders interpret the tone as dismissive, while the PM intended it to be factual. What communication model principle does this illustrate?
87 / 150
Question 88 of 150
In the interactive communication model (as opposed to the basic linear model), what is the KEY difference?
88 / 150
Question 89 of 150
A PM is communicating with stakeholders across three cultures: one that values direct, explicit communication, one that communicates indirectly through context and relationship, and one that prioritizes hierarchical formality. What type of noise is MOST likely to cause misunderstandings?
89 / 150
Question 90 of 150
A PM uses a multi-channel approach: weekly written reports, bi-weekly video calls, and monthly in-person meetings. What communication model principle supports this approach?
90 / 150
Question 91 of 150
During a video conference, the PM notices that a remote stakeholder's video is off and they are not responding to questions. The PM continues the meeting without addressing this. What communication principle is being violated?
91 / 150
Question 92 of 150
A PM is preparing a presentation for the executive committee. What encoding strategy should the PM use to minimize noise and maximize message reception?
92 / 150
Question 93 of 150
The concept of 'information overload' represents a specific type of noise in the communication model. A PM sends 15 detailed emails per day to stakeholders. Response rates have dropped to near zero. What is happening?
93 / 150
Question 94 of 150
A PM communicates a critical project risk to the sponsor in a hallway conversation. The sponsor later claims they were never informed. What communication principle was violated?
94 / 150
Question 95 of 150
A PM recognizes that different stakeholders process information differently — some prefer visual data (charts, diagrams), some prefer written narratives, and some prefer verbal discussions. What should the PM do?
95 / 150
Question 96 of 150
In a distributed team meeting, the PM presents important information while a team member is simultaneously chatting with a colleague about an unrelated topic. The team member later asks the PM to repeat the information. What concept from the communication model applies?
96 / 150
Question 97 of 150
A project team is experiencing frequent misunderstandings despite regular communication. The PM suspects 'filtering' is occurring — team members are modifying messages as they pass through organizational layers. What communication model phenomenon is this?
97 / 150
Question 98 of 150
The PM implements a 'communication confirmation' protocol where receivers must acknowledge critical messages within 24 hours and summarize their understanding. What communication model component does this strengthen?
98 / 150
Question 99 of 150
A PM discovers that the same message produced different reactions from two stakeholder groups: one group understood the urgency and took immediate action, while the other dismissed it as routine. What communication factor most likely caused this difference?
99 / 150
Question 100 of 150
A PM wants to reduce overall communication noise on the project. Which combination of actions is MOST effective?
100 / 150
Question 101 of 150
A PM needs to distribute the monthly status report to 40 stakeholders. Which communication method is MOST appropriate?
101 / 150
Question 102 of 150
A PM stores project documents, lessons learned, and reference materials on a shared project portal. Stakeholders access them as needed. What communication method is this?
102 / 150
Question 103 of 150
A PM needs to resolve a complex technical disagreement between two architects. Which communication method is MOST appropriate?
103 / 150
Question 104 of 150
A PM defaults to interactive communication (meetings) for all project communications. The team spends 60% of their time in meetings. What is the MAIN problem with this approach?
104 / 150
Question 105 of 150
A PM sends a push communication (email) announcing a significant scope change. Several stakeholders respond angrily, saying they should have been consulted before the decision. What communication method should the PM have used?
105 / 150
Question 106 of 150
A PM on a global project needs to share urgent safety information with all team members across 5 time zones immediately. Which communication approach is MOST effective?
106 / 150
Question 107 of 150
During sprint retrospectives in an agile project, the team uses interactive communication to discuss what went well, what did not, and what to improve. A remote team member suggests replacing retrospectives with written surveys (push). What would be lost?
107 / 150
Question 108 of 150
A PM categorizes all project communications into push, pull, or interactive. Which classification applies to a project dashboard that automatically updates with real-time metrics?
108 / 150
Question 109 of 150
A PM needs to deliver bad news about a project delay to a key client. The PM considers sending an email to avoid a difficult conversation. What is the BEST approach?
109 / 150
Question 110 of 150
A PM wants to collect lessons learned from the project team. What combination of communication methods would yield the MOST comprehensive results?
110 / 150
Question 111 of 150
A PM manages a project with strict regulatory documentation requirements. Every communication about compliance decisions must be documented and traceable. Which communication method is MOST appropriate for compliance discussions?
111 / 150
Question 112 of 150
A new team member joins the project midway through execution and needs to understand 6 months of project history. Which communication method is MOST efficient for their onboarding?
112 / 150
Question 113 of 150
A project team debates whether to use Slack (instant messaging) for project communications. Is Slack push, pull, or interactive?
113 / 150
Question 114 of 150
A PM communicates the same project update using three methods: email (push) to executives, portal posting (pull) for the broader organization, and a team meeting (interactive) for the project team. Why use different methods for the same information?
114 / 150
Question 115 of 150
A PM over-relies on pull communication, posting everything to the project portal but rarely pushing critical information directly to stakeholders. Project awareness is low and stakeholders frequently claim ignorance of important decisions. What should the PM change?
115 / 150
Question 116 of 150
A PM needs to determine the number of communication channels on a project with 12 team members including the PM. Using the formula Channels = n(n-1)/2, how many potential channels exist?
116 / 150
Question 117 of 150
A project team grows from 8 to 12 members. By what percentage do communication channels increase? (Channels = n(n-1)/2)
117 / 150
Question 118 of 150
A PM uses the communication channels formula to justify why a 50-person project needs a formal communication management plan. What does the formula reveal about large teams?
118 / 150
Question 119 of 150
A PM selects video conferencing for all team meetings despite some team members having unreliable internet connections. Several members frequently drop off calls. What communication planning principle was violated?
119 / 150
Question 120 of 150
A PM is choosing between synchronous (real-time) and asynchronous (time-delayed) communication tools for a team across 5 time zones with no overlapping business hours. Which approach is MOST practical for routine communications?
120 / 150
Question 121 of 150
A PM implements a new project management tool (e.g., Jira, Monday.com) but adoption is low. Team members continue using email and spreadsheets. What should the PM do?
121 / 150
Question 122 of 150
A project handles sensitive client data. The PM allows team members to discuss project details on personal messaging apps. What risk does this create?
122 / 150
Question 123 of 150
A PM is evaluating whether to use email or a project collaboration platform for day-to-day team communication. The team has 15 members working on interdependent tasks. What is the PRIMARY advantage of a collaboration platform over email?
123 / 150
Question 124 of 150
The communication channels formula shows 45 channels for a 10-person team. The PM creates sub-teams of 4, 3, and 3. How does this affect effective communication channels?
124 / 150
Question 125 of 150
A PM manages a project with strict compliance requirements. All decisions must have documented communication trails. What communication technology characteristic is MOST important?
125 / 150
Question 126 of 150
A PM discovers that critical project communications are happening in informal channels (hallway talks, lunch conversations) that are not captured in any system. What risk does this create?
126 / 150
Question 127 of 150
When selecting communication technology for a project, the PM should consider several factors. Which of the following is a comprehensive evaluation framework?
127 / 150
Question 128 of 150
A project team of 20 currently has 190 potential communication channels. A new stakeholder requirement adds 5 team members. How many channels will exist after the addition?
128 / 150
Question 129 of 150
A PM's organization mandates the use of Microsoft Teams for all project communications. However, an external vendor partner uses Slack exclusively. What should the PM do?
129 / 150
Question 130 of 150
A PM measures communication effectiveness and finds that stakeholders rate email updates as 'informative but not engaging.' Video updates from the PM get much higher engagement and satisfaction scores. What communication concept explains this?
130 / 150
Question 131 of 150
What is the PRIMARY purpose of a communications management plan?
131 / 150
Question 132 of 150
A communications management plan should address communication requirements. How should the PM determine what information each stakeholder needs?
132 / 150
Question 133 of 150
A PM creates a detailed communications management plan at the beginning of the project but never updates it during execution. Stakeholders complain they are not receiving relevant information. What went wrong?
133 / 150
Question 134 of 150
The communications management plan includes a 'communication matrix.' What does this matrix typically contain?
134 / 150
Question 135 of 150
A PM schedules weekly status meetings with the full 25-person project team. After 3 weeks, attendance drops and engagement is low. What communication planning mistake was made?
135 / 150
Question 136 of 150
A PM needs to report project status to three different audiences: the steering committee (monthly), the sponsor (bi-weekly), and the team (weekly). Should the PM create three different reports?
136 / 150
Question 137 of 150
The communications management plan should address potential communication barriers. Which of the following is a comprehensive list of common barriers?
137 / 150
Question 138 of 150
A PM discovers that project team members are communicating conflicting information to external stakeholders. Different team members provide different answers to the same questions. What communication planning element is missing?
138 / 150
Question 139 of 150
An agile project uses information radiators (visible boards showing sprint progress, burndown charts, impediments). How do information radiators fit into the communications management plan?
139 / 150
Question 140 of 150
A PM conducts a communication effectiveness review and discovers that stakeholders read only 30% of the weekly status email. What should the PM investigate?
140 / 150
Question 141 of 150
A PM manages a project where a previous communication breach led to confidential project information being leaked to competitors. What element should the communications management plan emphasize?
141 / 150
Question 142 of 150
A PM is closing a project and conducting a final communication assessment. What metrics should be used to evaluate communication effectiveness throughout the project?
142 / 150
Question 143 of 150
The PM receives feedback that stakeholders in a different cultural context feel disrespected by the direct, terse communication style used in status reports. What communication planning principle should guide the PM's response?
143 / 150
Question 144 of 150
A PM's communications management plan specifies escalation protocols. What should these protocols include?
144 / 150
Question 145 of 150
A PM realizes that the communications management plan, stakeholder engagement plan, and stakeholder register all contain related but inconsistent information about stakeholder communication preferences. What should the PM do?
145 / 150
Question 146 of 150
A PM identifies a key stakeholder as High Power / High Interest on the Power/Interest Grid, Definitive on the Salience Model (Power + Legitimacy + Urgency), and Resistant on the Stakeholder Cube. The Engagement Assessment Matrix shows them at 'Resistant' (C) with a desired level of 'Supportive' (D). What comprehensive engagement strategy should the PM develop?
146 / 150
Question 147 of 150
A PM discovers through stakeholder analysis that two 'Manage Closely' stakeholders have conflicting requirements and use completely different communication styles — one prefers detailed written analysis (push), while the other insists on face-to-face discussions (interactive). Both are equally powerful. How should the PM structure communication for an upcoming critical decision?
147 / 150
Question 148 of 150
A project team of 15 has grown to 25 due to a scope expansion. Communication channels increased from 105 to 300. Simultaneously, stakeholder analysis reveals 5 new 'Keep Satisfied' stakeholders and 3 new 'Manage Closely' stakeholders. What should the PM update?
148 / 150
Question 149 of 150
A PM conducts a retrospective and identifies that most project issues traced back to communication failures: a resistant stakeholder who was not identified early, push communication used for a sensitive decision, and semantic noise from jargon-heavy reports to non-technical stakeholders. What systemic improvement should the PM recommend?
149 / 150
Question 150 of 150
An organization is selecting a project management approach for a complex, politically sensitive initiative. The stakeholder landscape includes: 3 Definitive stakeholders (Salience Model), 8 High Power/High Interest stakeholders (Power/Interest Grid), significant cultural diversity, and a history of communication breakdowns. Using both stakeholder and communication analysis, what should the PM prioritize in the project approach?
150 / 150