1 / 150
2 / 150
Question 3 of 150
A PM is asked to calculate the NPV of a 3-year project. The initial investment is $500,000. Expected net cash flows are: Year 1 = $150,000, Year 2 = $200,000, Year 3 = $300,000. The discount rate is 10%. Using NPV = Sum(CF_t / (1+r)^t) - Initial Investment, what is the approximate NPV?
3 / 150
4 / 150
5 / 150
Question 6 of 150
An organization is evaluating three projects under a capital budget constraint of $1,000,000. Project X: Cost $600,000, NPV $120,000. Project Y: Cost $500,000, NPV $95,000. Project Z: Cost $450,000, NPV $110,000. Which combination maximizes total NPV within the budget?
6 / 150
7 / 150
8 / 150
9 / 150
10 / 150
11 / 150
12 / 150
13 / 150
14 / 150
15 / 150
16 / 150
17 / 150
18 / 150
19 / 150
20 / 150
21 / 150
22 / 150
23 / 150
24 / 150
25 / 150
26 / 150
27 / 150
28 / 150
29 / 150
30 / 150
Question 31 of 150
A project is 60% complete when the sponsor requests early termination due to a strategic pivot. The project has spent $600,000 of its $1,000,000 budget and delivered $400,000 in benefits so far. What is the ROI at the point of termination?
31 / 150
32 / 150
33 / 150
34 / 150
35 / 150
36 / 150
37 / 150
38 / 150
39 / 150
40 / 150
41 / 150
42 / 150
43 / 150
44 / 150
45 / 150
46 / 150
47 / 150
48 / 150
49 / 150
50 / 150
51 / 150
52 / 150
53 / 150
54 / 150
Question 55 of 150
A project has uneven cash flows: Year 1 = $50,000, Year 2 = $75,000, Year 3 = $200,000, Year 4 = $300,000. Initial investment = $300,000. A stakeholder argues the payback period is 1.5 years because $300,000 / $200,000 average annual flow = 1.5. What is wrong with this calculation?
55 / 150
56 / 150
57 / 150
58 / 150
59 / 150
Question 60 of 150
A project's initial investment is phased: $200,000 in Year 0, $150,000 in Year 1, and $100,000 in Year 2. Revenue begins in Year 2 at $250,000/year. How should the PM calculate the payback period?
60 / 150
61 / 150
62 / 150
63 / 150
64 / 150
65 / 150
66 / 150
67 / 150
68 / 150
69 / 150
70 / 150
71 / 150
72 / 150
73 / 150
74 / 150
75 / 150
76 / 150
77 / 150
78 / 150
79 / 150
80 / 150
81 / 150
82 / 150
83 / 150
84 / 150
85 / 150
86 / 150
87 / 150
88 / 150
89 / 150
90 / 150
91 / 150
92 / 150
93 / 150
94 / 150
95 / 150
96 / 150
97 / 150
98 / 150
99 / 150
100 / 150
101 / 150
102 / 150
103 / 150
104 / 150
105 / 150
106 / 150
107 / 150
108 / 150
109 / 150
110 / 150
111 / 150
112 / 150
113 / 150
114 / 150
115 / 150
116 / 150
117 / 150
118 / 150
119 / 150
120 / 150
121 / 150
122 / 150
123 / 150
124 / 150
125 / 150
126 / 150
127 / 150
128 / 150
129 / 150
130 / 150
131 / 150
132 / 150
133 / 150
134 / 150
135 / 150
136 / 150
137 / 150
138 / 150
139 / 150
140 / 150
141 / 150
142 / 150
143 / 150
144 / 150
145 / 150
Question 146 of 150
A portfolio selection committee is evaluating four projects. Project A: NPV=$300K, IRR=22%, PBP=2yr, BCR=1.8. Project B: NPV=$500K, IRR=15%, PBP=4yr, BCR=1.4. Project C: NPV=$200K, IRR=28%, PBP=1yr, BCR=2.5. Project D: NPV=-$50K, IRR=8%, PBP=6yr, BCR=0.9. The hurdle rate is 12%. Which project should be eliminated FIRST?
146 / 150
Question 147 of 150
A PM must recommend ONE project to the executive committee. The data: Project Alpha: NPV=$800K, ROI=40%, IRR=18%, PBP=3yr. Project Beta: NPV=$600K, ROI=55%, IRR=24%, PBP=1.5yr. Both require the same $1M investment. The organization is financially stable with a long-term growth strategy. Which project should the PM recommend and why?
147 / 150
148 / 150
149 / 150
150 / 150